About the Project
This project encompassed the Replacement of galvanized domestic cold and hot water risers and the mechanical room piping with the stainless steel schedule 10 piping and Viega stainless steel press fittings.
Har-Con installed a temporary PVC Schedule 80 cold water riser from one of the booster pumps in the level one mechanical room to the storage tank in the mechanical room in the penthouse on Level 25. Har-Con performed multiple shut downs of the mechanical rooms and of 3 floors at a time and replaced the hot and cold water risers with the stainless steel piping and Viega stainless steel press fittings. The piping was replaced through the pressure reducing stations and tied into the existing copper water piping serving each floor.